Current lead time and pricing data for electronic components.
Last Update :
22/03/2007
We are here to help.
If you are being told parts cannot be sourced, don't take NO for an
answer!
Lead Times and Pricing Trends
Summary
|
| Micro
Standard lead-time approx 12-16 wks.
Renesas 16 wks.
Maxim 20 wks.
Tosh 16 wks.
TI ahead at only 6-8 wks
|
Commodity Lin & Logic
Maxim 18 wks & Rohm 14 wks +.
STM surface mount back on alloc rest 12 wks.
Standard Lead-time approx 14-16 wks.
FSC offering around 20 wks.
TI extended 26 wks – test problems on most.
All old Burr Brown on alloc
|
Non- Commodity Lin & Logic
Standard Lin & Logic between 12-16 wks.
FSC now stable 12 wks.
TI offering 12-16 wks.
STM surface mount is on alloc rest 12 wks.
AD extended to 16 wks
|
| Memory
Standard lead-time 12-20 wks.
STM have gone from alloc to 10 wks.
BEWARE – TOSH now withdrawn. SRAM, NAND chips. |
Discretes
FSC have moved out to 22 wks.
INFN are at 12 wks.
STM surface mount is on alloc rest 12 wks.
Vishay 20 wks, some alloc.
All the rest at 12-18 wks. |
Other
FSC Opto see Everlight – 8 wks.
Vishay 20 wks, some alloc.
Tosh opto on alloc. |
Electrolytics
Standard lead-time is extending to approx.
18 wks.
Pan standard lead-time 18 wks – ask marketing for factory
improvement. |
Tantalums
Lead-times all over the place on Tants varying from
6-20 wks
Rohm no longer promoting. No quote for to new business.
Some HiCap
values are on extended leadtimes up to 20/24 wks.
Vishay 11-16 wks Kemet
6-20 wks |
Cap Ceramics
Lead-times now more under control at 8-18 wks
AVX,
Kemet & Epcos at only 8-12 wks.
The rest sit at around 12-18 wks.
Kemet &
AVX stock can be checked online, please contact us. |
| Inductors
Lead-times are extending approx. 12-16 wks.
Bourns 12 wks.
Epcos 4-15 wks, often stk 0805’s 9-12 wks.
Tyco at 12 wks.
Murata 10 wks
|
Protection
Lead-times range from 12-16 wks.
AVX & Bourns offering 12 wks.
Epcos 14 wks.
|
Resistors
Lead-times range from 6-16 wks.
Many RN73 (0805 10ppm’s) in stock, leadtime down to 6-8 wks.
Vishay CRCW series are currently 12-14 wks
|
Legend:
Increasing ↑ Stable ↔
Decreasing ↓
Last updated: 2nd March 2007
| Semiconductors - Standard Products |
|
Technology |
Supplier |
Lead Time |
Price |
Comments |
| LOGIC |
Fairchild |
↔ |
↔ |
Lead Times
8-16 wks |
| LOGIC |
NXP |
↔ |
↔ |
Lead Times
8-12 wks |
| LOGIC |
ON Semiconductor |
↔ |
↔ |
Lead Times
8-12 wks |
| LOGIC |
STMicroelectronics |
↓ |
↔ |
Lead Times
12-18 wks |
| LOGIC |
Texas Instruments |
↔ |
↔ |
Lead Times
6-12 wks |
| LINEAR |
National Semiconductor |
↔ |
↔ |
Lead Times
6-12 wks |
| LINEAR |
STMicroelectronics |
↓ |
↔ |
Lead Times
8-16 wks |
| LINEAR |
Texas Instruments |
↓ |
↔ |
Lead Times
4-8 wks |
| LINEAR |
Toshiba |
↔ |
↔ |
|
| LINEAR |
ON Semiconductor |
↔ |
↔ |
Lead Times
6-12 wks |
| LINEAR |
Vishay |
↔ |
↔ |
Lead Times
16-22 wks |
| DISCRETE |
ON Semiconductor |
↔ |
↔ |
Lead Times
8-12 wks |
| DISCRETE |
Vishay |
↔ |
↔ |
Lead Times
12 wks |
| DISCRETE |
Taiwan Semi |
↔ |
↔ |
Lead Times
12 wks |
| DISCRETE |
STMicroelectronics |
↔ |
↔ |
Lead Times
12-16 wks |
| DISCRETE |
NXP |
↔ |
↔ |
Lead Times
6-12 wks |
| POWER |
NXP |
Allocation |
↔ |
Heavy allocation |
| POWER |
STMicroelectronics |
↔ |
↑ |
Heavily constrained |
| POWER |
Vishay |
↔ |
↔ |
Lead Times
16-22 wks |
| POWER |
Fairchild |
↑ |
↔ |
Lead Times
30 wks |
| OPTOCOUPLERS |
Fairchild |
↔ |
↔ |
Lead Times
8-16 wks |
| OPTOCOUPLERS |
Sharp |
↔ |
↔ |
Lead Times
16-22 wks |
| OPTOCOUPLERS |
Toshiba |
↔ |
↔ |
Lead Times
16-22 wks |
| OPTOCOUPLERS |
Vishay |
↔ |
↔ |
Lead Times
6-8 wks |
| OPTOCOUPLERS |
Avago |
↔ |
↔ |
Lead Times
6-8 wks |
|
Supplier |
Technology |
Lead Time |
Price |
Comments |
| Atmel |
EEPROM (Serial) |
↔ |
↔ |
Serial EEPROM price stable, issues on 512k
and extending Lead Times on 16k |
| Atmel |
EEPROM (Parallel & Wireless) |
↔ |
↔ |
Price remains stable |
| Atmel |
EPROM |
↔ |
↔ |
Lead Times remain stable at between
ex-stock to 8 wks depending on density |
| Atmel |
Flash |
↓ |
↔ |
4-16 wks Lead Times no major issues |
| Cypress |
Slow SRAM |
↓ |
↓ |
Improvement in general Lead Times due to
new die and production mix. |
| Cypress |
Fast SRAM |
↔ |
↓ |
Improvement in general Lead Times due to
new die and production mix. Issues still on 2Mb and 4Mb |
| IDT |
Fast SRAM |
↔ |
↔ |
26 wks |
| Intel |
Flash |
↓ |
↔ |
4-8 wks |
| Microchip |
EEPROM |
↔ |
↔ |
Lead Times between
4-16 wks |
| Micron |
SDRAM |
↔ |
↓ |
4-6 wks |
| Micron |
DDR I and DDR II |
↔ |
↔ |
16 wks to allocation Mixed availability on
parts |
| Micron |
NAND Flash |
↔ |
↔ |
Samples and pre-production volumes only |
| NEC |
SRAM |
↔ |
↔ |
Lead Times 16 wks |
| Renesas |
SRAM |
↑ |
↔ |
Lead Times 16 wks |
| Samsung |
Fast SRAM |
↔ |
↔ |
4Mb IndTemp still ok, full production. |
| Samsung |
SDRAM |
Allocation |
↔ |
Parts on allocation upside available
dependant on density and Samsung production mix |
| Samsung |
DDR I and DDR II |
↔ |
↔ |
256Mb & 512Mb average Lead Times 4-6 wks,
1Gb 8-10 wks |
| Samsung |
NAND Flash |
↔ |
↓ |
None left on allocation, rest on average
7-9 wks. |
| Sharp |
SRAM (64k Only) |
EOL |
↑ |
On EOL now. |
| Spansion |
Flash |
↔ |
↓ |
No major supply issues Lead Times 4-16 wks
dependant on density and package |
|
STMicroelectronics |
EEPROM |
↔ |
↔ |
Lead Times now 4-16 wks |
|
STMicroelectronics |
EPROM |
↔ |
↔ |
No major supply issues Lead Times 4-16 wks
dependant on density and package |
|
STMicroelectronics |
NOR Flash |
↔ |
↔ |
Lead Times 4-16 wks no major supply issues |
|
STMicroelectronics |
NAND Flash |
↔ |
↓ |
Focus on 128Mb, 256Mb and 512Mb Joint
venture with Hynix. New for distribution customers |
| Toshiba |
SRAM |
Obsolete |
↑ |
All SRAMs which were left are EOL'd |
| Toshiba |
NAND Flash |
Allocation |
↓ |
Parts in short supply, EOL on 64Mb and
128Mb Price trends dependant on density |
| Semiconductors - Proprietary |
|
Supplier |
Technology |
Lead Time |
Price |
Comments |
| Analog Devices |
Analogue |
↔ |
↔ |
Yield issues on some specific Part
Numbers. Lead Times typically
12-16 wks overall.
Some parts on formal allocation.
Military parts 22 wks |
| Analog Devices |
DSP |
↔ |
↔ |
Yield issues on some specific Part
Numbers. Lead Times typically
12-16 wks overall.
Some parts on formal allocation |
| Altera |
FPGA |
↔ |
↔ |
Some Stratix II and Max II still on
allocation.
Lead time typically
6-12 wks |
| Atmel |
AVR-Micro's, (ATMEGA, ATTINY) |
↔ |
↔ |
AVR's 8-12 wks,
C51 core 16-18 wks |
| Cypress |
Low speed USB |
↔ |
↔ |
Lead Times 6-14 wks |
| Cypress |
HOTLinkII (parts beginning CYP, CYV, CYW) |
↔ |
↔ |
Lead Times appr.
6-8 wks |
| Cypress |
Low speed USB |
↔ |
↔ |
Lead Times appr.
18-20 wks |
| Freescale |
8-bit &16-bit Micros with embedded Flash |
↑ |
↔ |
Generally 8-bit and 16-bit Flash MCU's
Lead Times 22-26 wks due to increased demand. Improvement
expected in Q1'07 to be 14-16 wks |
| IR |
Power |
↔ |
↔ |
Capacity problems on DPAK, SO8 and D2PAK.
Lead Times 22-26 wks |
| LTC |
Data Converters |
↔ |
↔ |
Lead Times typically 4 wks |
| LTC |
Amplifiers / Comparators |
↔ |
↔ |
Lead Times typically 4 wks |
| LTC |
Power Management |
↔ |
↔ |
Lead Times typically 4 wks |
| LTC |
Interface |
↔ |
↔ |
Lead Times typically 4 wks |
| Micrel |
Ethernet (KSx) High Bandwidth (SYx) |
↔ |
↔ |
Lead Times 6-16 wks |
|
STMicroelectronics |
Regulator: Ppak and D2pak |
↑ |
↔ |
Lead Times 20 wks+ |
|
STMicroelectronics |
Rectifiers |
↑ |
↔ |
Lead Times 15-20 wks |
|
STMicroelectronics |
Protection |
↔ |
↔ |
Lead Times 11-15 wks |
Texas
Instruments |
High Performance Analogue INAx, OPAx, Ucx |
Allocation |
↔ |
Test capacity & qualifying issues. Old
legacy Burr Brown parts on formal allocation and Lead Times on
others still extended at 12-26 wks |
Texas
Instruments |
TMS320 - DSP's |
↔ |
↔ |
Lead Times are improving between 12-16 wks |
Texas
Instruments |
MSP430 - Micro's |
↔ |
↔ |
Lead Times are improving between 12-16 wks |
|
Supplier |
Technology |
Lead Time |
Price |
Comments |
| Sharp |
Displays |
Allocation |
↔ |
Extended Lead Times between 22-26 wks |
| All |
Displays |
↔ |
↔ |
General Lead Times between 12-16 wks on
Far East Suppliers. |
|
Product |
Package |
Lead Times |
Price |
Comments |
| Ceramic
Capacitors |
Surface Mount |
↔ |
↔ |
Murata high-caps extended Lead Times |
| Ceramic
Capacitors |
Leaded |
↑ |
↔ |
Lead Times 12 wks |
| Tantalum
Capacitors |
Surface Mount |
↔ |
↔ |
Kemet High-caps Lead Times up to 35 wks |
| Tantalum
Capacitors |
Leaded |
↔ |
↔ |
Lead Times 10 wks |
| Film Capacitors |
Box |
↔ |
↔ |
BCC film caps
Lead Times 22 wks |
| Electrolytic
Capacitors |
Small Can |
↓ |
↔ |
BCC Alu caps
Lead Times 22 wks |
| Electrolytic
Capacitors |
Large Can |
↓ |
↔ |
Lead Times 18 wks |
| Resistors |
Surface Mount |
↑ |
↔ |
Yageo PR/PF,RC0805,RC1206 Lead Times
increased to 15 wks |
| Resistors |
Leaded |
↔ |
↔ |
Lead Times 10 wks |
| Inductors |
|
↓ |
↔ |
Lead Times 10 wks |
| Crystals |
Surface Mount |
↔ |
↔ |
Lead Times 10 wks |
| Crystals |
Leaded |
↔ |
↔ |
Lead Times 10 wks |
| Fuses |
Standard |
↑ |
↔ |
Littelfuse parts have a general Lead Time
increase by 2 wks |
| Fuses |
Surface Mount |
↔ |
↔ |
Lead Times 10 wks |
| Fuses |
Resettable |
↑ |
↔ |
Lead Times 10 wks |
|
Supplier |
Technology |
Lead Time
Trend |
Price Trend |
Comments |
| 3M |
Headers,
IDC,
Cable/B-Board, Sockets |
↔ |
↑ |
Headers 3-8 wks
IDC 8-14 wks
Cable/B board
6-12 wks
Sockets 8 wks.
Some overdue delivery issues |
| Samtec |
Headers,
IDC,
Cable/B-Board,
Sockets |
↔ |
↑ |
Standard Lead Times
3 weeks |
| Tyco |
Headers,
IDC,
Cable/B-Board,
Sockets |
↔ |
↑ |
Headers 9-18 wks
IDC 9-18 wks
Cable/B board
9-20 wks
Sockets 12-22 wks. |
| Molex |
Headers,
IDC,
Cable/B-Board,
Sockets |
↔ |
↔ |
Headers 10-14 wks
IDC 7-15 wks
Cable/B board
11-16 wks
Sockets 8 wks.
Lead Times now stabilising. |
| FCI |
Headers,
IDC,
Cable/B-Board,
Sockets |
↑ |
↔ |
Headers 9-12 wks
IDC 10 wks
Cable/B board
8-12 wks
Sockets 10 wks. |
| FCI |
I/O,
Modular,
D-Sub |
↔ |
↔ |
I/O 5-14 wks
D-sub 10-14 wks |
| Molex |
I/O,
Modular,
D-Sub |
↔ |
↔ |
I/O 5-12 wks
D-sub 5-10 wks |
| Samtec |
I/O,
Modular,
D-Sub |
↔ |
| | |